Latest earned value measurement reports

It was Friday afternoon, a late November day in 2003, and Ron Katz, a purchas- ing agent for Robert L. Frank Construction, poured over the latest earned value measurement reports. The results kept pointing out the same fact; the Lewis project was seriously over budget. Man-hours expended to date were running 30 percent over the projection and, despite this fact, the project was not progressing sufficiently to satisfy the customer. Material deliveries had experienced several slippages, and the unofficial indication from the project scheduler was that, due to delivery delays on several of the project’s key items, the completion date of the coal liquefaction pilot plant was no longer possible.

Katz was completely baffled. Each day for the past few months as he reviewed the daily printout of project time charges, he would note that the pur- chasing and expediting departments were working on the Lewis project, even though it was not an unusually large project, dollarwise, for Frank. Two years ear- lier, Frank was working on a $300 million contract, a $100 million contract and a $50 million contract concurrently with the Frank Chicago purchasing depart- ment responsible for all the purchasing, inspection, and expediting on all three contracts. The Lewis project was the largest project in house and was valued at only $90 million. What made this project so different from previous contracts and caused such problems? There was little Katz felt that he could do to correct the situation. All that could be done was to understand what had occurred in an effort

Don't use plagiarized sources. Get Your Custom Essay on
Latest earned value measurement reports
Just from $10/Page
Order Essay

Robert L. Frank Construction Company

665

c17.qxd 12/21/12 7:00 PM Page 665

 

 

to prevent a recurrence. He began to write his man-hour report for requested by the project manager the next day.

COMPANY BACKGROUND

Robert L. Frank Construction Company was an engineering and construction firm serving the petroleum, petrochemical, chemical, iron and steel, mining, pharma- ceutical, and food-processing industries from its corporate headquarters in Chicago, Illinois, and its worldwide offices. Its services include engineering, pur- chasing, inspection, expediting, construction, and consultation.

Frank’s history began in 1947 when Robert L. Frank opened his office. In 1955, a corporation was formed, and by 1960 the company had completed con- tracts for the majority of the American producers of iron and steel. In 1962, an event occurred that was to have a large impact on Frank’s future. This was the merger of Wilson Engineering Company, a successful refinery concern, with Robert L. Frank, now a highly successful iron and steel concern. This merger greatly expanded Frank’s scope of operations and brought with it a strong period of growth. Several offices were opened in the United States in an effort to better handle the increase in business. Future expansions and mergers enlarged the Frank organization to the point where it had fifteen offices or subsidiaries located throughout the United States and twenty offices worldwide. Through its first twenty years of operations, Frank had more than 2,500 contracts for projects hav- ing an erected value of over $1 billion.

Frank’s organizational structure has been well suited to the type of work undertaken. The projects Frank contracted for typically had a time constraint, a budget constraint, and a performance constraint. They all involved an outside cus- tomer such as a major petroleum company or a steel manufacturer. Upon accep- tance of a project, a project manager was chosen (and usually identified in the proposal). The project manager would head up the project office, typically con- sisting of the project manager, one to three project engineers, a project control manager, and the project secretaries. The project team also included the necessary functional personnel from the engineering, purchasing, estimating, cost control, and scheduling areas. Exhibit I is a simplified depiction. Of the functional areas, the purchasing department is somewhat unique in its organizational structure. The purchasing department is organized on a project management basis much as the project as a whole would be organized. Within the purchasing department, each project had a project office that included a project purchasing agent, one or more project expeditors and a project purchasing secretary. Within the purchasing department the project purchasing agent had line authority over only the project expeditor(s) and project secretary. However, for the project pur- chasing agent to accomplish his goals, the various functions within the purchasing

666 ROBERT L. FRANK CONSTRUCTION COMPANY

c17.qxd 12/21/12 7:00 PM Page 666

 

 

Exhibit I. Frank organization

VP Eng. VP Control VP Procurement

Purchasing

Project A

Project B

Project C

Mechanical Piping Electrical Civil Estimate Schedule

667

c17.qxd 12/21/12 7:00 PM Page 667

 

 

department had to commit sufficient resources. Exhibit II illustrates the organi- zation within the purchasing department.

HISTORY OF THE LEWIS PROJECT

Since 1998, the work backlog at Frank has been steadily declining. The Rovery Project, valued at $600 million, had increased company employment sharply since its inception in 1997. In fact, the engineering on the Rovery project was such a large undertaking that in addition to the Chicago office’s participation, two other U.S. offices, the Canadian office, and the Italian subsidiary were heavily involved. However, since the Rovery project completion in 2001, not enough new

668 ROBERT L. FRANK CONSTRUCTION COMPANY

Exhibit II. Frank purchasing organization

Mgr. Procurement

Mgr. Buying, Esp., Insp.

Project A

Project B

Project C

Admin. Assistant

Chief Inspector

InspectionMgr. Buying Mgr. Traffic Chief Expediter

Buying Traffic Expediting

Project D

Project E

c17.qxd 12/21/12 7:00 PM Page 668

 

 

work was received to support the work force thus necessitating recent lay-offs of engineers, including a few project engineers.

Company officials were very disturbed with the situation. Frank’s company policy was to “maintain an efficient organization of sufficient size and resources, and staffed by people with the necessary qualifications, to execute projects in any location for the industries served by Frank.” However, the recent down- turn in business meant that there was not enough work even with the reduction in employees. Further cutbacks would jeopardize Frank’s prospects of obtaining future large projects as prospective clients look to contractors with a sufficient staff of qualified people to accomplish their work. By contrast, supporting employees out of overhead was not the way to do business, either. It became increasingly important to “cut the fat out” of the proposals being submitted for possible projects. Despite this, new projects were few and far between, and the projects that were received were small in scope and dollar value and therefore did not provide work for very many employees.

When rumors of a possible construction project for a new coal liquefaction pilot plant started circulating, Frank officials were extremely interested in bidding for the work. It was an excellent prospect for two reasons. Besides Frank’s des- perate need for work, the Lewis chemical process used in the pilot plant would benefit Frank in the long run by the development of state-of-the-art technology. If the pilot plant project could be successfully executed, when it came time to construct the full-scale facility, Frank would have the inside track as they had already worked with the technology. The full-scale facility offered prospects exceeding the Rovery project, Frank’s largest project to date. Top priority was therefore put on obtaining the Lewis project. It was felt that Frank had a slight edge due to successful completion of a Lewis project six years ago. The proposal submitted to Lewis contained estimates for material costs, man-hours, and the fee. Any changes in scope after contract award would be handled by change order to the contract. Both Lewis and Frank had excellent scope change control processes as part of their configuration management plans. The functional department affected would submit an estimate of extra man-hours involved to the project man- ager, who would review the request and submit it to the client for approval. Frank’s preference was for cost-plus-fixed-fee contracts.

One of the unique aspects stated in the Lewis proposal was the requirement for participation by both of Frank Chicago’s operating divisions. Previous Frank contracts were well suited to either Frank’s Petroleum and Chemical Division (P & C) or the Iron and Steel Division (I & S). However, due to the unusual chem- ical process, one that starts with coal and ends up with a liquid energy form, one of the plant’s three units was well suited to the P & C Division and one was well suited to the I & S Division. The third unit was an off-site unit and was not of par- ticular engineering significance.

History of the Lewis Project 669

c17.qxd 12/21/12 7:00 PM Page 669

 

 

The award of the contract six weeks later led to expectations by most Frank personnel that the company’s future was back on track again. The project began inauspiciously. The project manager was a well-liked, easy-going sort who had been manager of several Frank projects. The project office included three of Frank’s most qualified project engineers.

In the purchasing department, the project purchasing agent (PPA) assigned to the project was Frank’s most experienced PPA. Bill Hall had just completed his assignment on the Rovery Project and had done well, considering the magnitude of the job. The project had its problems, but they were small in comparison to the achievements. He had alienated some of the departments slightly but that was to be expected. Purchasing upper management was somewhat dissatisfied with him in that, due to the size of the project, he didn’t always use the normal Frank pur- chasing methods; rather, he used whatever method he felt was in the best interest of the project. Also, after the Rovery project, a purchasing upper management reshuffling left him in the same position but with less power and authority rather than receiving a promotion he had felt he had earned. As a result, he began to sub- tly criticize the purchasing management. This action caused upper management to hold him in less than high regard but, at the time of the Lewis Project, Hall was the best person available.

Due to the lack of float in the schedule and the early field start date, it was necessary to fast start the Lewis Project. All major equipment was to be pur- chased within the first three months. This, with few exceptions, was accom- plished. The usual problems occurred such as late receipt of requisition from engineering and late receipt of bids from suppliers.

One of the unique aspects of the Lewis project was the requirement for pur- chase order award meetings with vendors. Typically, Frank would hold award meetings with vendors of major equipment such as reactors, compressors, large process towers, or large pumps. However, almost each time Lewis approved pur- chase of a mechanical item or vessel, it requested that the vendor come in for a meeting. Even if the order was for an on-the-shelf stock pump or small drum or tank, a meeting was held. Initially, the purchasing department meeting attendees included the project purchasing agent, the buyer, the manager of the traffic depart- ment, the chief expeditor, and the chief Inspector. Engineering representatives included the responsible engineer and one or two of the project engineers. Other Frank attendees were the project control manager and the scheduler. Quite often, these meetings would accomplish nothing except the reiteration of what had been included in the proposal or what could have been resolved with a phone call or even e-mail. The project purchasing agent was responsible for issuing meeting notes after each meeting.

One day at the end of the first three-month period, the top-ranking Lewis rep- resentative met with Larry Broyles, the Frank project manager.

670 ROBERT L. FRANK CONSTRUCTION COMPANY

c17.qxd 12/21/12 7:00 PM Page 670

 

 

Lewis rep: Larry, the project is progressing but I’m a little concerned. We don’t feel like we have our finger on the pulse of the project. The information we are getting is sketchy and untimely. What we would like to do is meet with Frank every Wednesday to review progress and resolve problems.

Larry: I’d be more than happy to meet with any of the Lewis people because I think your request has a lot of merit.

Lewis rep: Well, Larry, what I had in mind was a meeting between all the Lewis people, yourself, your project office, the project purchasing agent, his assistant, and your scheduling and cost control people.

Larry: This sounds like a pretty involved meeting. We’re going to tie up a lot of our people for one full day a week. I’d like to scale this thing down. Our pro- posal took into consideration meetings, but not to the magnitude we’re talking about.

Lewis rep: Larry, I’m sorry but we’re footing the bill on this project and we’ve got to know what’s going on.

Larry: I’ll set it up for this coming Wednesday. Lewis rep: Good.

The required personnel were informed by the project manager that effective immediately, meetings with the client would be held weekly. However, Lewis was dissatisfied with the results of the meetings, so the Frank project manager informed his people that a premeeting would be held each Tuesday to prepare the Frank portion of the Wednesday meeting. All of the Wednesday participants attended the Tuesday premeetings.

Lewis requests for additional special reports from the purchasing department were given into without comment. The project purchasing agent and his assistants (project started with one and expanded to four) were devoting a great majority of their time to special reports and putting out fires instead of being able to track progress and prevent problems. For example, recommended spare parts lists were normally required from vendors on all Frank projects. Lewis was no exception. However, after the project began, Lewis decided it wanted the spare parts recom- mendations early into the job. Usually, spare parts lists are left for the end of an order. For example, on a pump with fifteen-week delivery, normally Frank would pursue the recommended spare parts list three to four weeks prior to shipment, as it would tend to be more accurate. This improved accuracy was due to the fact that at this point in the order, all changes probably had been made. In the case of the Lewis project, spare parts recommendations had to be expedited from the day the material was released for fabrication. Changes could still be made that could dramatically affect the design of the pump. Thus, a change in the pump after receipt of the spare parts list would necessitate a new spare parts list. The time involved in this method of expediting the spare parts list was much greater than the

History of the Lewis Project 671

c17.qxd 12/21/12 7:00 PM Page 671

 

 

time involved in the normal Frank method. Added to this situation was Lewis’s request for a fairly involved biweekly report on the status of spare parts lists on all the orders. In addition, a full time spare parts coordinator was assigned to the project.

The initial lines of communication between Frank and Lewis were initially well defined. The seven in-house Lewis representatives occupied the area adja- cent to the Frank project office (see Exhibit III). Initially, all communications from Lewis were channeled through the Frank project office to the applicable functional employee. In the case of the purchasing department, the Frank project office would channel Lewis requests through the purchasing project office. Responses or return communications followed the reverse route. Soon the volume of communications increased to the point where response time was becoming unacceptable. In several special cases, an effort was made to cut this response time. Larry Broyles told the Lewis team members to call or go see the functional per- son (i.e., buyer or engineer) for the answer. However, this practice soon became the rule rather than the exception. Initially, the project office was kept informed

672 ROBERT L. FRANK CONSTRUCTION COMPANY

Exhibit III. Floor plan—Lewis project teams

Project Manager

Assistant to Project

Manager

Procurement Advisor

Inspection Coordinator

Vacant Project Control

Manager

Chief Project Engineer

Project Manager

Project Engineer

Project Engineer

Project Engineer

Assistant Project Engineer

Engineer

Engineer

Cost Control

Grey boxed text Indicates Lewis Personnel

Normal text Indicates Frank Personnel

c17.qxd 12/21/12 7:00 PM Page 672

 

 

of these conversations, but this soon stopped. The Lewis personnel had integrated themselves into the Frank organization to the point where they became part of the organization.

The project continued on, and numerous problems cropped up. Vendors’ material delays occurred, companies with Frank purchase orders went bankrupt, and progress was not to Lewis’s satisfaction. Upper management soon became aware the problems on this project due to its sensitive nature, and the Lewis project was now receiving much more intense involvement by senior management than it had previously. Upper management sat in on the weekly meetings in an attempt to pacify Lewis. Further problems plagued the project. Purchasing management, in an attempt to placate Lewis, replaced the project purchasing agent. Ron Katz, a promising young MBA graduate, had five years of experience as an assistant to several of the project purchasing agents. He was most recently a project purchas- ing agent on a fairly small project that had been very successful. It was thought by purchasing upper management that this move was a good one, for two reasons. First, it would remove Bill Hall from the project as PPA. Second, by appointing Ron Katz, Lewis would be pacified, as Katz was a promising talent with a suc- cessful project under his belt.

However, the project under direction of Katz still experienced problems in the purchasing area. Revisions by engineering to material already on order caused serious delivery delays. Recently requisitioned material could not be located with an acceptable delivery promise. Katz and purchasing upper management, in an attempt to improve the situation, assigned more personnel to the project, personnel that were more qualified than the positions dictated. Buyers and upper-level pur- chasing officials were sent on trips to vendors’ facilities that were normally han- dled by traveling expediters. In the last week the Lewis representative met with the project manager, Broyles:

Lewis rep: Larry, I’ve been reviewing these man-hour expenditures, and I’m disturbed by them.

Larry: Why’s that? Lewis rep: The man-hour expenditures are far outrunning project progress.

Three months ago, you reported that the project completion percentage was 30 percent, but according to my calculations, we’ve used 47 percent of the man hours. Last month you reported 40 percent project completion and I show a 60 percent expenditure of man-hours.

Larry: Well, as you know, due to problems with vendors’ deliveries, we’ve really had to expedite intensively to try to bring them back in line.

Lewis rep: Larry, I’m being closely watched by my people on this project, and a cost or schedule overrun not only makes Frank look bad, it makes me look bad.

Larry: Where do we go from here?

History of the Lewis Project 673

c17.qxd 12/21/12 7:00 PM Page 673

 

 

Lewis rep: What I want is an estimate from your people on what is left, man- hour wise. Then I can sit down with my people and see where we are.

Larry: I’ll have something for you the day after tomorrow. Lewis rep: Good.

The functional areas were requested to provide this information, which was reviewed and combined by the project manager and submitted to Lewis for approval. Lewis’s reaction was unpleasant, to say the least. The estimated man- hours in the proposal were now insufficient. The revised estimate was for almost 40 percent over the proposal. The Lewis representative immediately demanded an extensive report on the requested increase. In response to this, the project man- ager requested man-hour breakdowns from the functional areas. Purchasing was told to do a purchase order by purchase order breakdown of expediting and inspection man-hours. The buying section had to break down the estimate of the man-hours needed to purchase each requisition, many of which were not even issued. Things appeared to have gone from bad to worse.

674 ROBERT L. FRANK CONSTRUCTION COMPANY

c17.qxd 12/21/12 7:00 PM Page 674


Get Professional Assignment Help Cheaply

Buy Custom Essay

Are you busy and do not have time to handle your assignment? Are you scared that your paper will not make the grade? Do you have responsibilities that may hinder you from turning in your assignment on time? Are you tired and can barely handle your assignment? Are your grades inconsistent?

Whichever your reason is, it is valid! You can get professional academic help from our service at affordable rates. We have a team of professional academic writers who can handle all your assignments.

Why Choose Our Academic Writing Service?

  • Plagiarism free papers
  • Timely delivery
  • Any deadline
  • Skilled, Experienced Native English Writers
  • Subject-relevant academic writer
  • Adherence to paper instructions
  • Ability to tackle bulk assignments
  • Reasonable prices
  • 24/7 Customer Support
  • Get superb grades consistently

Online Academic Help With Different Subjects

Literature

Students barely have time to read. We got you! Have your literature essay or book review written without having the hassle of reading the book. You can get your literature paper custom-written for you by our literature specialists.

Finance

Do you struggle with finance? No need to torture yourself if finance is not your cup of tea. You can order your finance paper from our academic writing service and get 100% original work from competent finance experts.

Computer science

Computer science is a tough subject. Fortunately, our computer science experts are up to the match. No need to stress and have sleepless nights. Our academic writers will tackle all your computer science assignments and deliver them on time. Let us handle all your python, java, ruby, JavaScript, php , C+ assignments!

Psychology

While psychology may be an interesting subject, you may lack sufficient time to handle your assignments. Don’t despair; by using our academic writing service, you can be assured of perfect grades. Moreover, your grades will be consistent.

Engineering

Engineering is quite a demanding subject. Students face a lot of pressure and barely have enough time to do what they love to do. Our academic writing service got you covered! Our engineering specialists follow the paper instructions and ensure timely delivery of the paper.

Nursing

In the nursing course, you may have difficulties with literature reviews, annotated bibliographies, critical essays, and other assignments. Our nursing assignment writers will offer you professional nursing paper help at low prices.

Sociology

Truth be told, sociology papers can be quite exhausting. Our academic writing service relieves you of fatigue, pressure, and stress. You can relax and have peace of mind as our academic writers handle your sociology assignment.

Business

We take pride in having some of the best business writers in the industry. Our business writers have a lot of experience in the field. They are reliable, and you can be assured of a high-grade paper. They are able to handle business papers of any subject, length, deadline, and difficulty!

Statistics

We boast of having some of the most experienced statistics experts in the industry. Our statistics experts have diverse skills, expertise, and knowledge to handle any kind of assignment. They have access to all kinds of software to get your assignment done.

Law

Writing a law essay may prove to be an insurmountable obstacle, especially when you need to know the peculiarities of the legislative framework. Take advantage of our top-notch law specialists and get superb grades and 100% satisfaction.

What discipline/subjects do you deal in?

We have highlighted some of the most popular subjects we handle above. Those are just a tip of the iceberg. We deal in all academic disciplines since our writers are as diverse. They have been drawn from across all disciplines, and orders are assigned to those writers believed to be the best in the field. In a nutshell, there is no task we cannot handle; all you need to do is place your order with us. As long as your instructions are clear, just trust we shall deliver irrespective of the discipline.

Are your writers competent enough to handle my paper?

Our essay writers are graduates with bachelor's, masters, Ph.D., and doctorate degrees in various subjects. The minimum requirement to be an essay writer with our essay writing service is to have a college degree. All our academic writers have a minimum of two years of academic writing. We have a stringent recruitment process to ensure that we get only the most competent essay writers in the industry. We also ensure that the writers are handsomely compensated for their value. The majority of our writers are native English speakers. As such, the fluency of language and grammar is impeccable.

What if I don’t like the paper?

There is a very low likelihood that you won’t like the paper.

Reasons being:

  • When assigning your order, we match the paper’s discipline with the writer’s field/specialization. Since all our writers are graduates, we match the paper’s subject with the field the writer studied. For instance, if it’s a nursing paper, only a nursing graduate and writer will handle it. Furthermore, all our writers have academic writing experience and top-notch research skills.
  • We have a quality assurance that reviews the paper before it gets to you. As such, we ensure that you get a paper that meets the required standard and will most definitely make the grade.

In the event that you don’t like your paper:

  • The writer will revise the paper up to your pleasing. You have unlimited revisions. You simply need to highlight what specifically you don’t like about the paper, and the writer will make the amendments. The paper will be revised until you are satisfied. Revisions are free of charge
  • We will have a different writer write the paper from scratch.
  • Last resort, if the above does not work, we will refund your money.

Will the professor find out I didn’t write the paper myself?

Not at all. All papers are written from scratch. There is no way your tutor or instructor will realize that you did not write the paper yourself. In fact, we recommend using our assignment help services for consistent results.

What if the paper is plagiarized?

We check all papers for plagiarism before we submit them. We use powerful plagiarism checking software such as SafeAssign, LopesWrite, and Turnitin. We also upload the plagiarism report so that you can review it. We understand that plagiarism is academic suicide. We would not take the risk of submitting plagiarized work and jeopardize your academic journey. Furthermore, we do not sell or use prewritten papers, and each paper is written from scratch.

When will I get my paper?

You determine when you get the paper by setting the deadline when placing the order. All papers are delivered within the deadline. We are well aware that we operate in a time-sensitive industry. As such, we have laid out strategies to ensure that the client receives the paper on time and they never miss the deadline. We understand that papers that are submitted late have some points deducted. We do not want you to miss any points due to late submission. We work on beating deadlines by huge margins in order to ensure that you have ample time to review the paper before you submit it.

Will anyone find out that I used your services?

We have a privacy and confidentiality policy that guides our work. We NEVER share any customer information with third parties. Noone will ever know that you used our assignment help services. It’s only between you and us. We are bound by our policies to protect the customer’s identity and information. All your information, such as your names, phone number, email, order information, and so on, are protected. We have robust security systems that ensure that your data is protected. Hacking our systems is close to impossible, and it has never happened.

How our Assignment Help Service Works

1. Place an order

You fill all the paper instructions in the order form. Make sure you include all the helpful materials so that our academic writers can deliver the perfect paper. It will also help to eliminate unnecessary revisions.

2. Pay for the order

Proceed to pay for the paper so that it can be assigned to one of our expert academic writers. The paper subject is matched with the writer’s area of specialization.

3. Track the progress

You communicate with the writer and know about the progress of the paper. The client can ask the writer for drafts of the paper. The client can upload extra material and include additional instructions from the lecturer. Receive a paper.

4. Download the paper

The paper is sent to your email and uploaded to your personal account. You also get a plagiarism report attached to your paper.

smile and order essay GET A PERFECT SCORE!!! smile and order essay Buy Custom Essay


Place your order
(550 words)

Approximate price: $22

Calculate the price of your order

550 words
We'll send you the first draft for approval by September 11, 2018 at 10:52 AM
Total price:
$26
The price is based on these factors:
Academic level
Number of pages
Urgency
Basic features
  • Free title page and bibliography
  • Unlimited revisions
  • Plagiarism-free guarantee
  • Money-back guarantee
  • 24/7 support
On-demand options
  • Writer’s samples
  • Part-by-part delivery
  • Overnight delivery
  • Copies of used sources
  • Expert Proofreading
Paper format
  • 275 words per page
  • 12 pt Arial/Times New Roman
  • Double line spacing
  • Any citation style (APA, MLA, Chicago/Turabian, Harvard)

Our guarantees

Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.

Money-back guarantee

You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.

Read more

Zero-plagiarism guarantee

Each paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.

Read more

Free-revision policy

Thanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.

Read more

Privacy policy

Your email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.

Read more

Fair-cooperation guarantee

By sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.

Read more
error: Content is protected !!
Open chat
1
Need assignment help? You can contact our live agent via WhatsApp using +1 718 717 2861

Feel free to ask questions, clarifications, or discounts available when placing an order.
  +1 718 717 2861           + 44 161 818 7126           [email protected]
  +1 718 717 2861         [email protected]